Difference between revisions of "Rollout"
Line 1: | Line 1: | ||
− | Working on rollout strategies we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time. | + | Working on rollout strategies, we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time. |
Field explanations | Field explanations |
Latest revision as of 15:52, 29 November 2012
Working on rollout strategies, we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time.
Field explanations
-Number of Sites - Number of physical locations requiring resources
-Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time
-Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live
-Weeks of Post Live Support - The number of weeks that a site will be given post-live resources
-Number of resources Left in Support role per site - The number of resources to support in the Post-live support
-Number of resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria
-Weeks to complete all sites - Calculation of how long it will take to cycle through all sites
-Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource
-Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace