Working on rollout strategies we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy.  Based on this, we created the attached spreadsheet.  The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live.  The sheet has the ability to calculate by number of sites or providers.  The sides would be used seperately not at the same time.
+
Working on rollout strategies, we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy.  Based on this, we created the attached spreadsheet.  The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live.  The sheet has the ability to calculate by number of sites or providers.  The sides would be used seperately not at the same time.
  
 
Field explanations
 
Field explanations
  
Number of Sites - Number of physical locations requiring resources
+
-Number of Sites - Number of physical locations requiring resources
Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time
+
 
Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live
+
-Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time
Weeks of Post Live Support - The number of weeks that a site will be given post-live resources
+
 
# resources Left in Support role per site - The number of resources to support in the Post-live support
+
-Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live
# resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria
+
 
Weeks to complete all sites - Calculation of how long it will take to cycle through all sites
+
-Weeks of Post Live Support - The number of weeks that a site will be given post-live resources
Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource
+
 
Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace
+
-Number of resources Left in Support role per site - The number of resources to support in the  
 +
Post-live support
 +
 
 +
-Number of resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria
 +
 
 +
-Weeks to complete all sites - Calculation of how long it will take to cycle through all sites
 +
 
 +
-Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource
 +
 
 +
-Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace
  
 
[[Image:Go-Live Resource Calculator.xls]]
 
[[Image:Go-Live Resource Calculator.xls]]

Latest revision as of 15:52, 29 November 2012

Working on rollout strategies, we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time.

Field explanations

-Number of Sites - Number of physical locations requiring resources

-Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time

-Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live

-Weeks of Post Live Support - The number of weeks that a site will be given post-live resources

-Number of resources Left in Support role per site - The number of resources to support in the Post-live support

-Number of resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria

-Weeks to complete all sites - Calculation of how long it will take to cycle through all sites

-Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource

-Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace

File:Go-Live Resource Calculator.xls