Working on rollout strategies we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time. | Working on rollout strategies we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time. | ||
+ | |||
+ | Field explanations | ||
+ | |||
+ | Number of Sites - Number of physical locations requiring resources | ||
+ | Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time | ||
+ | Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live | ||
+ | Weeks of Post Live Support - The number of weeks that a site will be given post-live resources | ||
+ | # resources Left in Support role per site - The number of resources to support in the Post-live support | ||
+ | # resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria | ||
+ | Weeks to complete all sites - Calculation of how long it will take to cycle through all sites | ||
+ | Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource | ||
+ | Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace | ||
[[Image:Go-Live Resource Calculator.xls]] | [[Image:Go-Live Resource Calculator.xls]] |
Revision as of 15:25, 26 July 2007
Working on rollout strategies we found it helpful to have a tool that would enable us to calculate the amount of resources necessary to support a given rollout strategy. Based on this, we created the attached spreadsheet. The spreadsheet is a great tool for estimating based on averages or resourcing a particular go-live. The sheet has the ability to calculate by number of sites or providers. The sides would be used seperately not at the same time.
Field explanations
Number of Sites - Number of physical locations requiring resources Simultaneous Sites to Go-live - How many physical locations requiring resources will be going live at the same time Week 1 Resources per Site - How many resources will be at each site week 1 of the go-live Weeks of Post Live Support - The number of weeks that a site will be given post-live resources
- resources Left in Support role per site - The number of resources to support in the Post-live support
- resources to maintain pace - Calculation based on the above telling how many resources would be necessary to rollout with those criteria
Weeks to complete all sites - Calculation of how long it will take to cycle through all sites Resource cost per week - Variable defining the weekly cost in dollars for a go-live resource Net Cost - Calculation based on the number of resources to maintain pace, weekly cost and number of weeks to maintain pace